No single outage is the same but Scheck’s Boiler Group sailed through Dominion’s outage downstate at Kincaid, Illinois. Scheck Industrial’s Project Team mobilized a work force of over 50 tradecraft and successfully completed the outage on two units as planned.
Unit One
- Removed three layers of catalyst in the SCR
 - Installed two layers of catalyst and associated seals
 - Removed and changed elevation and reinstall sonic horns on 2 catalyst layers
 - Installed thirteen air cannons on the top catalyst elevation along with associated piping, supports, guides, air tanks and control panels
 - Removed and replaced One Gas Recirculation fan rotor
 
Unit Two
- Remove three layers of catalyst in the SCR
 - Installed two layers of catalyst and associated seals
 - Removed and changed elevation and reinstall sonic horns on 2 catalyst layers
 - Installed thirteen air cannons on the top catalyst elevation along with associated piping, supports, guides, air tanks and control panels
 
		
			
				Posted on February 14, 2013			
		
			
				 
			
			
			
				 
			
			
			
				 
			
			
				 
			
		
				
						
		